Obviously the scope of work will dictate how long any home remodeling project takes to complete. Also, the Contractors’ work load will also dictate the time frame. Say for instance your job is one of 5 jobs the Contractor has going. Yours may not be his first priority, therefore your job will get less attention and take longer to complete. Roadrunner only performs one job at a time, so your job is always first priority. So, having said that, here are some general time frames it should take to complete a bathroom remodel if workers are there every day:
Shower remodel in solid surface with standard glass installation – 3 working days
Shower remodel in tile -7 days (8-10 days longer for custom glass installation)
8×5 complete bathroom remodel in solid surface – 8-10 working days
8×5 complete bathroom remodel in tile & stone – 15-20 working days (once again longer with custom glass)
Complete Master bath remodel in solid surface – 12-15 working days
Complete Master Bath remodel in tile and stone – 25-30 working days
So, with workers there every day, bathroom remodeling project can take anywhere from 3 – 30 working days. If it takes longer than that, your job is not a top priority.